Week 2 – Building project WilTec: Ground Works
The second week was marked by a bad weather, snow in early October in the region of Aachen, sleet at a height of 150 m above sea level, does that mean a bad sign with respect to the winter season or is it something of a freak of nature? Fortunately, there was no delay.
- The ground works have been completed, the loading dock has been excavated.
- The foundations for both warehouses have been excavated.
- 60 m³ of concrete have been poured into the foundation trenches.