Winter vacation after 10 weeks of construction
The last 3 weeks before beginning of the holidays once again have been marked by time pressure on the construction site of WilTec Wildanger Technik GmbH, Ernst-Abbe-Str. 2 in Eschweiler.
However, all phases of construction have delivered more than just in time:
- The company Schlun has laid a concrete channel of approx. 300m and a diameter of 40 cm and 50 cm respectively. There have been made ditches for the supply and so on. It has turned out to be a bit of a challenge because there is a channel to a depth of 5 m whereas at the same time the construction road had to remain open and free for the supply.
- The roofer has sealed hall 1
- Within only 9 days, the rails for the Stow Mobile have been assembled by the company Stow Deutschland GmbH
Not least, thanks to the very good coordination of our general contractor Valeres Industriebau GmbH, the concrete could flow on December, 17.
The Company Induplan GmbH, located in our neighbouring town Stolberg has started its works on concrete in the morning of December 17. The final one of the totally 48 concrete mixers has arrived at 7 o´clock p.m. and the last one of the employees of Induplan Industrieböden has left the site at 7 o´clock p.m. on Friday 18.
The floor made of a mirror-smooth concrete has been the last major step in hall 1 and is going to „rest“ now for a period of 28 days. Only then the supply and assembly of the shelving system is going to start, having a weight of 113 tons.
So, WilTec Wildanger Technik GmbH will be able to start the operation of the warehouse in early February, just 4 months after the construction project has been started.
As of 04.01.2016, the outside facilities are measured. At the same time the remaining works on hall 2 are started. The concreting works of hall 2 is planned for January 26, 2016.
Leave a Reply